Lynx as a platform   General Army topics

Started 4/4/22 by graylion; 14055 views.
schnuersi

From: schnuersi

25/7/22

This is a common criticism of unmanned turrets.

Which may or may not be valid. Current experience by users indicates that its not valid. Of course this depends on several variables. For example how the turret and the crew stations are equiped. Which in turn has direct influence on cost.

Mr. T (MrT4)

From: Mr. T (MrT4)

25/7/22

Although looking at the Czech tender Unmanned turret, and many other unmanned turrets its seems they are actually higher than the manned turrets. and have additionally higher hull roof to accommodate crew under it

schnuersi

From: schnuersi

25/7/22

The height of a turret any hull depend on the desired characteristics and resulting design.

If the turret is not supposed to have a significant Intrusion into the hull, eg. no turret basket, it has to be higher if a large gun elevation is desired from a conventional gun mounting.

The deterimning factor for hull hight usually is not where the turret crew is situated but its about the required ergonomics and protection level.

Never the less vehicle height is of rather low relevance nowadays. As long as the railway transport dimension limits are met there are few constrains.

Mr. T (MrT4)

From: Mr. T (MrT4)

25/7/22

It seems no other IFV met Czech Rail transport standard dimensions , And as far as i understand the unmanned turrets also had issues with armoring as most were not capable of matching the vehicle armoring even in max up-armored versions. The turret on the pics was a Kongsberg MCT30 that is only Level 1 protected and can't be up-armored to match the protection levels of the vehicle which was one of the Czech requrements..

schnuersi

From: schnuersi

25/7/22

The Czech decision to buy the CV90 has online one reason: money.

The CV90 is the cheapest solution and the manufacturer made the required concessions for local production and involvement of the local industry.

The bidding and the program was formally stopped last year not for technical reasons but because the required documentation and/or above mentioned local involvement requirements have not been met by either bidder. Because of this no bid was concidered acceptable. The decision to buy the CV90 now was made as a government business decision.

P.S.: There is a NATO standard for rail transport and all contestants meet it. Demounting secondary armament and external armor and skirts is acceptable and pretty common.

Mr. T (MrT4)

From: Mr. T (MrT4)

25/7/22

I can imagine cost was a major factor, ,Slovak tender where CV90 also won supposedly had the following bids. 

One of the remarks vs the unmanned turret was that it can't be operated without power while a maned one can still be operated and fired under manual power? *Altough i would imagine Puma turret with glass optical channels could probably be operated manually if someone ordered it as such.

  152 vehicles,  110 infantry fighting vehicles, 15 command vehicles, 9 reconnaissance vehicles, 3 armored personnel carriers, 9 self-propelled 120-mm mortars, 3 engineering vehicles , 3 ARVs

CV9030 Mk IV 1,669,093,939 €
CV9035 MK IV 1,688,845,030 €
ASCOD 1,724,882,231 €
KF41 Lynx 1,854,089,739 €

Total procurement costs of the offered vehicles including VAT and infrastructure costs

* we are paying more for Boxer through OCCAR than either Czech or Slovak CV90MK4 cost

https://below-the-turret-ring.com/armored-vehicles/slovakia-announces-the-cv90-mk-iv-as-its-preferred-ifv/

schnuersi

From: schnuersi

25/7/22

Mr. T (MrT4) said:

One of the remarks vs the unmanned turret was that it can't be operated without power while a maned one can still be operated and fired under manual power? *Altough i would imagine Puma turret with glass optical channels could probably be operated manually if someone ordered it as such.

Extremly unlikely. It at the very least would require a major redesign.
Basically no modern all electric turret can be operated without power. Usually if redundancy behond the engine, APU and on bord power storage is required the solution is to add additional storage.
Operating the turret manually is de facto an outdated concept. Even if it is possible power loss is a mission kill and demands immediate disengage and fall back.

Mr. T (MrT4) said:

I can imagine cost was a major factor

Usually it allmost the only factor that counts. Neither the Slovaks nor the Czech really bothere testing. They just read trough the documentation and compared them. The entire Slovak test program of the provided test vehicles took them five days. The Czech have not been much better. Under this condition a sensible comparison of technical details isn't possible. Which means the decision can only be made based on numbers on paper.

RovingPedant

From: RovingPedant

25/7/22

Mr. T (MrT4) said...

* we are paying more for Boxer through OCCAR than either Czech or Slovak CV90MK4 cost

Are we? Looks like the numbers there are about £10m per vehicle but I thought that the UK Boxer buy was £5m per vehicle.

Mr. T (MrT4)

From: Mr. T (MrT4)

25/7/22

Not quite but getting there it started at 5.6 million in 2018 now it's north of 8.6mio and the number just keeps climbing and i reckon before it is actually all over , it will be north of 10mio Eur a piece .

Its a purely political buy, no trials, no competition, no tender just uncompetitive order at OCCAR and it seems it comes a water-tight legal immunity for OCCAR over any possible wrongdoing, funny enough same folk who now ordered Boxer were previously involved with Patria AMV shenanigans where millions in bribes were paid, but in that deal, we were buying 136 vehicles for 263mio, now we are getting 45 for near 390mio Eur , cost is artificially being kept lower than it will actually be in the end as some of the armaments and all the coms are now in removed from the contract price meaning they will make an annex somewhere down the line. The original contract before the ''creative cost cutting'' was 412 mio Eur for 45 boxers, now suddenly specs dropped the coms all together (this alone will be multimillion item), night lighting , tow hook, heated fuel tanks, heat masking of the engine compartment and air inlet and exhaust, commander's hatch with periscopes, laser irradiation sensing system,  and some of the previously 30mm armed boxers got 12.7mm RWS instead.  A hefty price for a 8x8 APC  pretending to be an IFV

We have seen similar shenanigans with Partia AMV  at one stage creative cost cutting hit the order and suddenly 30mm canon and turreted mortars all disappeared from the order , as Elbit RWS turned out to absolute turds unable to hit jack shit and prone to freezing up so much more expensive Kongsbers RWS ate away the armament budget 

schnuersi

From: schnuersi

26/7/22

Thiy sounds more like a case of horrible project management driving cost to extreme levels than the manufacturer charging an extreme prime.   

TOP